Migrating between collaboration platforms is among the highest-risk IT projects. A single DNS mistake can leave an entire team without email for hours. This article covers the checklist we follow every time we move a team from Google Workspace to Microsoft 365. The principles are the same in the other direction.
Why companies migrate
Before getting into the technical side, the reason for the migration needs to be clear. The ones we hear most often:
- Consolidating applications. The team already uses Office 365 from a parent company, or the reverse.
- Compliance. Certain certifications such as ISO or SOC 2 are easier to meet on a single platform.
- License pricing. A corporate-level agreement gives a large discount on one of the platforms.
- Specific feature needs. For example, Teams or SharePoint features that are not available in Google Workspace.
If the only reason is wanting to try something new, it is better to wait. Migration takes time and carries real risk, so it should be done once the benefits can be measured.
The three phases of a migration
Phase 1: Inventory (1–2 weeks)
What you need to document before touching anything:
- User list: names, email aliases, groups, and job titles, mapped to the structure on the destination platform.
- Mailbox sizes: so you know who has 100 GB and can estimate migration time.
- Shared drives and shared mailboxes: the part most often missed.
- Third-party integrations: applications that sign in through a Google or Microsoft account. The data is in the Admin Console under Security, in the OAuth apps section.
- Automations and scripts: Google Apps Script, Power Automate, and Zapier.
- Aliases and mailing lists:
info@,sales@, andhr@all need to move too. - Current DNS configuration: save it as a screenshot or export it to a file.
The result of this phase is a migration plan document that spells out what moves, where, and when.
Phase 2: Limited pilot (1 week)
Avoid moving all users at once. Pick 5–10 users for a pilot, using these criteria:
- They represent different kinds of usage, for example an admin, a salesperson, and an engineer
- They are willing to be the first group to try it
- They are not in the most critical roles. Preferably not the founder or the head of sales
Move them, watch for unusual cases, then fix the configuration. Things that usually come up at this stage:
- Email filters that did not carry over
- Calendar events with external attendees whose organizer changed
- File sharing permissions that were not mapped correctly
- Integrations that need to be authorized again
Phase 3: Full migration and cutover (2–4 weeks)
Once the pilot succeeds, the full migration can run in batches of 20–50 users per day, or all at once. For teams of more than 100 people, we always choose batches.
The cutover window is when the MX record is changed, usually on a weekend, and it takes 2–4 hours. During that time:
- New email already arrives on the destination platform
- Email still left on the old platform is synced in a follow-up pass
- DNS propagation is monitored, for example with
digor an online DNS checker
DNS and MX cutover
The MX cutover is the hardest step to undo. How to prepare:
- Lower the TTL of all DNS records to 300 seconds, at least 24 hours before the cutover, so the change spreads quickly.
- Prepare a rollback plan: record all the old DNS values and make sure the rollback steps are known.
- Schedule it for a weekend or outside working hours, and tell your team there is a maintenance window.
- Monitor actively. For the first two hours after the cutover, watch incoming and outgoing email on both platforms.
Example weekend cutover schedule
| Time | Activity |
|---|---|
| Friday 18:00 | TTL has been lowered since 24 hours earlier |
| Saturday 09:00 | Final sync of all mailboxes |
| Saturday 10:00 | MX record switched to the new platform |
| Saturday 10:00–12:00 | DNS propagation and monitoring |
| Saturday 12:00 | Test incoming and outgoing email across different providers |
| Saturday 12:00–Sunday | Follow-up sync for email still arriving on the old platform |
| Monday 09:00 | Team starts working on the new platform |
Risks that are often missed
1. Calendar invitations to external parties
Events created by your users and already accepted by external parties, such as clients or vendors, sometimes break after migration. For important events like contract signings or product demos, resend the invitation from the new platform.
2. Email filters and rules
Complex filters, such as automatic forwarding, auto-replies, and conditional labeling, often do not carry over correctly. Document the important filters before the migration, and recreate them manually if needed.
3. Differences between Google Drive and OneDrive permissions
Google Drive has more granular permission settings than OneDrive. If you use shared drives with complicated restrictions, the mapping will not be exactly the same. Review and simplify the structure before migrating.
4. OAuth applications
Applications that sign in through Sign in with Google need to be re-authorized through Sign in with Microsoft after the migration. Compile the list and ask users to re-authorize within the first 48 hours.
Rollback plan
The rollback plan must be clear before the cutover is carried out. The document should include at least:
- A list of the old DNS records and their values, ready to copy back
- The names of the users with admin access on both platforms
- The threshold for when to roll back, for example more than 30% of users not receiving email for more than one hour
- A sample notification message to the team in case the rollback is actually carried out
Most migrations never need this plan. Its value is in being ready when one does.
When to bring in a professional service
Migration for a team of fewer than 10 people can be done in-house if an engineer is familiar with the process. For teams of more than 50 people, we recommend getting help. Not because the work is hard, but because a zero-data-loss target demands full attention that is hard to share with daily work.